I have checked all of my settings in the main sheet and dependencies are not turned on nor predecessors, the box remains grey? I also have ensured that in the details panel, it is not read only.
By any chance is the finish date calculated by durations based on a start date or by a formula? I don't have the dynamic view, but in reports when a field is calculated with formulas it is uneditable.
Mike is correct. Also, make sure the date column is not locked in the main sheet.
If the finish date is assigned in the dependencies settings in the Gantt View then you will not be able to change it. I think that is the case even if the dependencies check box is not checked.
Hi Marc,
Is it the same for all rows? Are you using any Field Logic rules?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Thanks This was driving me crazy!! once I Changed the date to another date column in dependencies (although not active) it worked.
Is anyone else having issues setting up a new Data Mesh? I am getting "Unexpected Error from Smartsheet API" then Data Mesh reloads.
Hello, A few of my datamesh have stopped running citing missing sheets. The sheets never got moved and are still there. Any insight into it? It has created a huge backlog for me.
Hello, We may have identified the cause of the DataMesh access issue I’ve been experiencing. Our IT administrator, Mike Hoke, noticed that I appear as a Plan User with full permissions, but I am showing as a non-member of the organization. His theory is that when I originally started using Smartsheet, I may have created an…