I have checked all of my settings in the main sheet and dependencies are not turned on nor predecessors, the box remains grey? I also have ensured that in the details panel, it is not read only.
By any chance is the finish date calculated by durations based on a start date or by a formula? I don't have the dynamic view, but in reports when a field is calculated with formulas it is uneditable.
Mike is correct. Also, make sure the date column is not locked in the main sheet.
If the finish date is assigned in the dependencies settings in the Gantt View then you will not be able to change it. I think that is the case even if the dependencies check box is not checked.
Hi Marc,
Is it the same for all rows? Are you using any Field Logic rules?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Thanks This was driving me crazy!! once I Changed the date to another date column in dependencies (although not active) it worked.
My organization has access to both EAP features and Table View, alongside the increase in limits associated with that. Despite this, one of my colleagues cannot seem to use Data Shuttle to upload more than 20,000 rows worth of data. I've seen bits and pieces of information suggesting a per-sheet/table opt-in, but cannot…
In my source report being used for a datamesh I have a column that is a formula column with a nested IF statement. The destination sheet is set-up to be a text/number field. Other columns work on the same source report are meshing, the one that is a column formula is not…is that the issue here? Thank you
The desired flow is: Smartsheet form is completed which includes three key pieces of info: Name, Email, Waiver This creates a new row in a Smartsheet A Power Automate flow is triggered where it checks specifically the Waiver (which is a dropdown either needed or not needed). If needed, the flow continues. I built an…