Hi, I'm new to Smastsheet, I have entered several tasks and sub tasks in my project, but they are not displaying in the Gantt chart. Any ideas?
Hi Tony,
Welcome to the Community and the wonderful world of Smartsheet!
Have you added dates and set up the Project Settings?
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Hi Andrée
Thanks for the reply, I think I've added everything necessary, I've attached a screenshot...
Tony
Happy to help!
Are the years correct? Should it be 2017 and 2019?
You're right, missed it completely :-)
Thanks for your help
I'm always happy to help!
Easy to miss!
Glad we found the reason!
I'm looking for a way to attach notes to a sheet that isn't attached to a specific row. Rows for many of my sheets are cleared out in preparation for the next iteration of the project, and I need a notes/comments field that remains with the sheet even when the rows do not.
I have a workspace that I am looking to move items from into a new workspace. The reason I want to do this is becasue there are individuals that have access to the original workspace that do not need access to everything that is currently in the workspace. In the original workspace is a MAIN document that holds all…
How to use Smartsheet AI/automation to automically write project status?