Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
Hello
I have a Due Date column and Completion Date column, how do I set up a formula to show when the completion date is past the due date and highlights it?
Thanks
Hi
In order to do this I believe you need a "helper" column. This is a column set up on the sheet to provide some logic which will drive your conditional format. The helper column doesn't need to be visible.
I would set up a checkbox column called something like Is Overdue? with the following formula =IF([Completion Date]@row > [Date Due]@row, 1, 0)
Then in the conditional formatting screen you would use the Is Overdue column to define the formatting for the Completion Date column. See screen shot below.
Hope this helps
Debbie
Hi Amanda,
You'll need to use a so-called helper column with a formula that checks the dates and then use that for the conditional formatting rule.
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Would that work?
I hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
@Amanda Ollerenshaw
How did it go? Did you get it working?
✅Did this post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer. It will make it easier for others to find a solution or help to answer!
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.