I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
Its very frustrating when you are adding multiple columns and having to use the slide bar to move to the end and then click the 3 dots and add another column. Seems there has to be an easier more productive way.
Hello, I am using an Appsheet app to update a Smartsheet 'metadata' sheet with a status. I have various other sheets that will then be updated based on unique ID's as their status changes on the metadata sheet. Since Smartsheet cannot run a Workflow on cell's changed with cross-sheet references, I have created a "helper"…
Hello! Happy New Year. I have an intake form and i would like to receive notification in my email when any person submits a request. It seems sometimes i get the notification and others times, i do not. There is a delay. Now i am not getting any notification. I am looking at the management automation workflow and i don't…