Lead and Lag start time columns
RKLRpp
✭✭
Any clever hacks to have smartsheet show the leading and lagging start dates according to multiple predecessor relationships?
Answers
-
Hi @RKLRpp,
Lag and Lead times should be added to the Predecessor column along with the multiple Predecessor relationships. Use the pencil (edit) icon that appears when clicking into a Predecessor cell. You can also type the Predecessors manually, but you might want to use the editor at first to help yourself best learn the format required.
Just a reminder: negative Lag is used to show Lead time.
This results in your Start and End Date columns to be updated accordingly (along with the Duration column, or course.)
BRgds,
-Ray
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!