I need to trigger notifications based on workdays. If I create a helper column using the WORKDAY formula, what do I base the # of days on?
Example: Notification to be triggered 3 days ahead of deadline which falls on a Monday. Notification would need to be sent that previous Thursday, not Saturday.
Best Answer
-
You would use the WORKDAY function and use negative numbers to output a date prior to the starting date.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Answers
-
You would use the WORKDAY function and use negative numbers to output a date prior to the starting date.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
Gracias @Paul Newcome. Thanks for your help.
-
Happy to help. 👍️
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives