Workday formula helper column
Marcela Hernandez
✭✭✭✭
Hello,
I need to trigger notifications based on workdays. If I create a helper column using the WORKDAY formula, what do I base the # of days on?
Example: Notification to be triggered 3 days ahead of deadline which falls on a Monday. Notification would need to be sent that previous Thursday, not Saturday.
Best Answer
-
You would use the WORKDAY function and use negative numbers to output a date prior to the starting date.
Answers
-
You would use the WORKDAY function and use negative numbers to output a date prior to the starting date.
-
Gracias @Paul Newcome. Thanks for your help.
-
Happy to help. 👍️
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives