Is there a way to adjust the timeline view of the High Level Project Plan Report widget? Right now, it shows the gantt chart with a daily timeline - not exactly high level :) I would like this view to show one month per column

Answers

  • Lolguin
    Lolguin ✭✭

    Hi @Yakshita Srivastava,

    On your main Smartsheet, try right clicking on the headers that shows the months and dates about the Gantt chart. Click on Zoom out as many times as needed to show months instead of days.

    Save and check your report. If I remember correctly, it should show that high level view that you have set on the sheet.

    Hope this helps. Good luck!