Formula not working

azerty64
✭✭
Hello,
can you explain this error to me?
The formula returns me the value 0 for a project that lasts one day
Thank you
Tags:
Best Answer
-
Hi @azerty64,
March 26th is a Sunday, so it is not counted as a working day - hence the NETWORKDAYS formula gives this result while working fine for the April 27th (a Thursday) line above.
Hope this explains it for you!
Answers
-
Hi @azerty64,
March 26th is a Sunday, so it is not counted as a working day - hence the NETWORKDAYS formula gives this result while working fine for the April 27th (a Thursday) line above.
Hope this explains it for you!
-
oh ok that makes sense...thank a lot !
Have good day !
Help Article Resources
Categories
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!