Formula not working

azerty64
azerty64 ✭✭
edited 02/20/23 in Formulas and Functions

Hello,

can you explain this error to me?

The formula returns me the value 0 for a project that lasts one day

Thank you

Tags:

Best Answer

  • Nick Korna
    Nick Korna ✭✭✭✭✭✭
    Answer ✓

    Hi @azerty64,

    March 26th is a Sunday, so it is not counted as a working day - hence the NETWORKDAYS formula gives this result while working fine for the April 27th (a Thursday) line above.

    Hope this explains it for you!