Multi-Tier Control Center | Changing Tier References
Hello Community,
Has anyone solved for how to change the tier references so that you can move a lower tier to a different upper tier?
Example:
Market (Top Tier) | Program (Middle Tier) | Project (Bottom Tier)
Given that we have to trigger the Market before the Program and the program before the Project in order to establish the right relationships, is there a way to change associations after the fact without having to retrigger anything?
Here's an ugly diagram to illustrate the reference change we're trying to make (without retriggering Project D).
Any help would be appreciated!
Thank you.
Answers
-
While you can amend reporting, to fully change over like this you would need to reprovision the project under the correct Program.
Please submit your feature request to the Product team by creating an Idea Post in the Smartsheet Product Feedback and Ideas topic. This will allow other users to vote on your enhancement idea and add their use-cases for the Product team to see.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives