Report by task owner - view

KarineMul22_TPg
✭✭✭
Hello,
Let's say I have created a report for all Open Actions across the different projects, I can order it by Task Owner, but then how can each task owner only has sight of his own tasks, is that possible?
Or do I need to go the long route and create a report per task owner?
Thank you
Karine
Answers
-
You would create a filter that is set to "Current User".