Work week Formula help

Jon Barto
✭✭✭✭✭
Do anyone know a formula to calculate the "work week" from a start date.
So see attached image. I can calculate what week in the year it is. but I need the yellow column to reflect the work week from the start date (the first green date in this case tuesday 4-4) The colors in green are imported from another sheet.
So I have numbers in the helper column that I would like it to report. week 1, 2, 3 ect.
Start date could be any workday.
Answers
-
Generally, if your dates are within the same calendar year: =WEEKNUMBER(Date@row)-WEEKNUMBER($Date$1)
If not, there'd be a slightly complicated additive to the formula that would account for the shift... may require a helper column.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 68K Get Help
- 474 Global Discussions
- 209 Use Cases
- 517 Announcements
- 5.6K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 85 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!