Need formula for % Complete of 3 specific rows in sheet
Hi -
My project has 3 phases in it and I would like to be able to show not only the % Complete of each phase but for the project overall. I have each phase working by enabling the dependencies and it is already calculating for those but I cannot get a formula to work to calculate the over all % Complete for Row 1.
Does anyone know the right formula to use? Thanks in advance!
Best Answer
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Answers
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
-
THANK YOU Paul!!! I don't know what I didn't think of that before! Greatly appreciate your help!!
-
Happy to help. 👍️
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!