Need formula for % Complete of 3 specific rows in sheet
Hi -
My project has 3 phases in it and I would like to be able to show not only the % Complete of each phase but for the project overall. I have each phase working by enabling the dependencies and it is already calculating for those but I cannot get a formula to work to calculate the over all % Complete for Row 1.
Does anyone know the right formula to use? Thanks in advance!
Best Answer
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
Answers
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
-
THANK YOU Paul!!! I don't know what I didn't think of that before! Greatly appreciate your help!!
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.7K Get Help
- 406 Global Discussions
- 218 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!