Need formula for % Complete of 3 specific rows in sheet
MisfitStormer
ββ
Hi -
My project has 3 phases in it and I would like to be able to show not only the % Complete of each phase but for the project overall. I have each phase working by enabling the dependencies and it is already calculating for those but I cannot get a formula to work to calculate the over all % Complete for Row 1.
Does anyone know the right formula to use? Thanks in advance!
Tags:
Best Answer
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
Answers
-
If you are using dependencies, you should be able to just indent all of the phase rows so that they are children of the top row.
-
THANK YOU Paul!!! I don't know what I didn't think of that before! Greatly appreciate your help!!