How to put both estimated & planned dates on a sheet?
Chiara_maz
✭✭
Hello,
I work in a company that supervises multiple construction projects accross Europe. We have a report with all the projects that our construction partners consult in order to plan their resources for the right time.
The issue is that the dates are not necessarly exact and we need to find a way to distinguish the estimated dates vs planned ones in the report. Do you have any ideas?
Tags:
Answers
-
Have you looked into using the Baseline feature in each of the individual sheets?
-
I have tried but without success. Is it possible to see the Baseline in a report?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.6K Get Help
- 403 Global Discussions
- 215 Industry Talk
- 455 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 56 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives