few weeks post we added the tasks , we needed to add new shared tasks , when we filled the start and end dates , they didn't reflect in the baseline start and end date ,
as workaround , I had to reset the baseline then it could reflect all tasks start and end dates , but this is not practical to keep resenting the baseline whenever we need to add new task
please advise