Resource Overallocation
Good morning,
I am managing a project with some very aggressive timelines using the Project Tracking and Rollup template set. I have added a column for Allocation %. My organization is in the process of purchasing enterprise licences, but currently we are just using a business licence, so I don't believe that we have access to resource management.
Is there a formula I can use to flag resource conflicts until we get our enterprise licences? Thank you
Answers
-
Hi There,
Not sure if your account is new, but you might still find "Resource Views" within Smartsheet, even in the business plan that you can leverage on. I have attached a screenshot. You can create a view to see all users in your Smartsheet account and their allocation across projects. The best way would be to go for Resource Management by Smartsheet, when you have the budget for it.
Thanks,
Aravind GP| Delivery Manager
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.7K Get Help
- 438 Global Discussions
- 152 Industry Talk
- 497 Announcements
- 5.3K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 77 Community Job Board
- 508 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!