Resource Overallocation
Good morning,
I am managing a project with some very aggressive timelines using the Project Tracking and Rollup template set. I have added a column for Allocation %. My organization is in the process of purchasing enterprise licences, but currently we are just using a business licence, so I don't believe that we have access to resource management.
Is there a formula I can use to flag resource conflicts until we get our enterprise licences? Thank you
Answers
-
Hi There,
Not sure if your account is new, but you might still find "Resource Views" within Smartsheet, even in the business plan that you can leverage on. I have attached a screenshot. You can create a view to see all users in your Smartsheet account and their allocation across projects. The best way would be to go for Resource Management by Smartsheet, when you have the budget for it.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.2K Get Help
- 360 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 444 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!