Status Column Change to Record Date of Change
Hello,
I am developing metrics for a group at my company and need some help. They do not log when they mark something as complete by date just by status. The date of the status change is in the cell history but I was wondering if there was a way to write a formula to show when a status is set to completed it records the date in a separate column. Does anyone have any experience with a formula like this? I am not sure where to start.
Thank you!
Tim
Best Answer
-
Hi @tim.curtin
The "Record a Date" feature is found within the Automation tab. First add a date column to your sheet and then go "Create Workflow from Template", scroll to the bottom and choose "Record the date when specificed criteria are met". It will explain what it does. From there the options are pretty straight forward. Let me know if you have any questions.
Thanks,
Matt
Answers
-
Hi @tim.curtin
The "Record a Date" feature is found within the Automation tab. First add a date column to your sheet and then go "Create Workflow from Template", scroll to the bottom and choose "Record the date when specificed criteria are met". It will explain what it does. From there the options are pretty straight forward. Let me know if you have any questions.
Thanks,
Matt
-
Hi @tim.curtin
I hope you're well and safe!
To add to Matt's excellent advice/answer.
If you need to store the time too, you can use my method described below.
More info:
Would that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi All
Does the "record a date" automation always enter the date in US timezone as it is putting the date as yesterday for me in Australia?
Thanks
HR
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.7K Get Help
- 434 Global Discussions
- 136 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 64 Community Job Board
- 481 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!