Extra Day Duration?

I'm confused. This is my first time using Smartsheet for scheduling. I think I have an extra day appearing in each of my durations?
ID 88 depends on ID 80, which completes on 6/17/24.
ID 88 is a 5 day duration showing it is starting on a Monday 6/17/24 and ending Monday 6/24/24? Isn't that 6 days?
I'm expecting to see either ID 88 show that it is starting Tuesday 6/17/24 ending on Monday 6/24/24 - Or - starting Monday 6/17/24 and ending on Friday 6/21/24.
I feel like I'm missing something very obvious.
Thanks!
Answers
-
I forgot the visual...
-
Hi @Wondercat
I hope you're well and safe!
Start with checking your Project Settings.
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives