Updating Duration on Dynamic View
Hi all,
I was wondering, in the regular grid view of a Smartsheet, if I update a start date or duration, the end date will automatically update without saving. I created a dynamic view where I want people to be able to update the end date, but it's locked since it's included in dependencies. As a work around I am having people update their start date and duration, but they have to save and reload in order to see the updated end date. Is there a way to see the updated end date instantaneously similar to grid view?
Thank you!
Answers
-
Hey @stepht1219
I dont think you can do that through Dynamic View.
For the fields to refresh in Dynamic View you have to save it.
Hopefully someone here comes up with a great idea to workaround that!