Updating Duration on Dynamic View

Hi all,

I was wondering, in the regular grid view of a Smartsheet, if I update a start date or duration, the end date will automatically update without saving. I created a dynamic view where I want people to be able to update the end date, but it's locked since it's included in dependencies. As a work around I am having people update their start date and duration, but they have to save and reload in order to see the updated end date. Is there a way to see the updated end date instantaneously similar to grid view?

Thank you!

Answers

  • Itai Perez
    Itai Perez ✭✭✭✭✭✭

    Hey @stepht1219

    I dont think you can do that through Dynamic View.

    For the fields to refresh in Dynamic View you have to save it.

    Hopefully someone here comes up with a great idea to workaround that!

    Itai Perez

    If you found my comment helpful any reaction, Insightful, Awsome etc... would be appreciated🙂

    https://www.linkedin.com/in/itai-perez/