How can I filter the work breakdown structure (WBS) 1 decimal point?
I'm trying to figure out how to share the view of the WBS by only 1 decimal. (1.1, 1.2, ...3.3, 3.4, etc.) I do not want it to exceed more than 1 decimal (1.1.2, 1.1.3, ...3.3.1, etc.) - Is there a way to filter the column by this way?
Answers
-
@Daniel Rico If your rows are indented then add a column that calculates the level... =COUNT(ANCESTORS(Primary@row)). Your filter can exclude anything where the level is greater than 3