Updating Project Stage Advancement formula
We have a current formula for Project Stage Advancement, that updates the Project Stage field when all tasks under in the section have been marked 100% and a task in the next section has been marked In Progress.
=IFERROR(INDEX([Task Name]:[Task Name], MATCH(MAX(COLLECT([Start Date]:[Start Date], Status:Status, OR(@cell = "In Progress", @cell = "Complete"), Hierarchy:Hierarchy, =2)), [Stage Helper]:[Stage Helper], 0)), "")
We would like to update our process and formula from checking if every task is complete in the stage to check if the [Advancement Task] column =1 and if that task is 100% complete. The [Advancement Task]=1 and being 100% complete would start the next Project Stage.
Current Process:
I've tried to update the formula, but all of my attempts have lead to Invalid Argument or Unparsable results. Any help with a new formula would be apprecitated.
Best Answer
-
Hi @Jenni N,
To update your process and formula from checking if every task is complete in the stage to checking if the [Advancement Task] column =1 and if that task is 100% complete you can try the following:
- You’d want to add a helper criteria into your Advancement Task formula that looks to see if the current row is a Level 2 hierarchy (Grey)
- If it is, then check to see if the Advancement Task with a 1 is at 100%.
- If it is, return the text “Advancement Complete”
- Then in your original formula you can add [Advancement Task]:[Advancement Task], "Advancement Complete" as a criteria.
The formula would be as follows:
=IFERROR(INDEX([Task Name]:[Task Name], MATCH(MAX(COLLECT([Start date]:[Start date], Status:Status, OR(@cell = "In Progress", @cell = "Complete"), Hierarchy:Hierarchy, =2, [Advancement Task]:[Advancement Task], "Advancement Complete")), [Stage Helper]:[Stage Helper], 0)), "")
See the following screenshots of the formula for reference:
Cheers,
Hamza
Answers
-
Hi @Jenni N,
To update your process and formula from checking if every task is complete in the stage to checking if the [Advancement Task] column =1 and if that task is 100% complete you can try the following:
- You’d want to add a helper criteria into your Advancement Task formula that looks to see if the current row is a Level 2 hierarchy (Grey)
- If it is, then check to see if the Advancement Task with a 1 is at 100%.
- If it is, return the text “Advancement Complete”
- Then in your original formula you can add [Advancement Task]:[Advancement Task], "Advancement Complete" as a criteria.
The formula would be as follows:
=IFERROR(INDEX([Task Name]:[Task Name], MATCH(MAX(COLLECT([Start date]:[Start date], Status:Status, OR(@cell = "In Progress", @cell = "Complete"), Hierarchy:Hierarchy, =2, [Advancement Task]:[Advancement Task], "Advancement Complete")), [Stage Helper]:[Stage Helper], 0)), "")
See the following screenshots of the formula for reference:
Cheers,
Hamza
-
@Hamza1, thank you so much for taking the time to not only respond to my request but also with screenshots. I appreciate your help.
This has me so close to the outcome I am looking for. I need to project stage to advance to the next Hierarchy 2 when the next checked task is greater than 0% (the status is "In Progress"). i I updated the Advancement task formula to take that into consideration, but Project Stage won't update.
For example, the project stage is reporting as:
However, I would expect it to be reporting 07- Design Development because the first task in that section is In Progress.
-
I figured it out, changing the checked task under 07-Design Development to just 1% wasn't a high enough percentage to get the hierarchy 2 row to change to "In Progress". Once I changed the checked task to 10% the Project Stage updated to 07-Design Development as expected.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.6K Get Help
- 403 Global Discussions
- 215 Industry Talk
- 455 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 56 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!