Working with Calendar Days instead of Work Days
For some of the project sheets that I use, I want to have calendar days instead of work days (Mon-Fri). Firstly, is there a way to update my account settings to have this be the standard for my account? Secondly, what would be the way to go about this on each project?
Thanks!
Answers
-
You can use elapsed days in your durations to make it ignore the working/non-working days piece by using "e" in front of the duration. This does not work for lag or lead time though.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives