Working with Calendar Days instead of Work Days
For some of the project sheets that I use, I want to have calendar days instead of work days (Mon-Fri). Firstly, is there a way to update my account settings to have this be the standard for my account? Secondly, what would be the way to go about this on each project?
Thanks!
Answers
-
You can use elapsed days in your durations to make it ignore the working/non-working days piece by using "e" in front of the duration. This does not work for lag or lead time though.