Update schedule based on progress complete

ash_barridge1
ash_barridge1 ✭✭
edited 10/31/23 in Smartsheet Basics

Im trying to update the schedule based on progress complete so that any tasks that are incomplete the remaining work is rescheduled as of todays date. Thanks

Answers

  • leonastomenio
    leonastomenio ✭✭✭✭

    Hi Ash,

    You could do this using the sheet automation. First, you need your trigger which is the column where it is identified as complete or incomplete, then add the Record a date as action which will automatically record today's date.