Update schedule based on progress complete

Options
ash_barridge1
ash_barridge1 ✭✭
edited 10/31/23 in Smartsheet Basics

Im trying to update the schedule based on progress complete so that any tasks that are incomplete the remaining work is rescheduled as of todays date. Thanks

Answers

  • leonastomenio
    leonastomenio ✭✭✭✭
    Options

    Hi Ash,

    You could do this using the sheet automation. First, you need your trigger which is the column where it is identified as complete or incomplete, then add the Record a date as action which will automatically record today's date.