I have a smartsheet that isn't adding the duration correctly.
I have a 7day task starting 11/15, so this should end on 11/22. On a coworker's smartsheet this task is 7d, starts on 11/15 and ends on the 11/22, as expected.
If I make this task 0 days, it ends on 11/15, and if I make it 1 day, it also ends on 11/15, which is inconsistent. To get my version of smartsheet to end on the 22nd, I have to make this a 8 day task, which is illogical.
There are no predecessors set for this task. I've tried this as a parent and a child, and the behavior is the same. I've turned "dependencies enabled" on and off, neither fixes this. What setting could be causing this?
I have the work week set inclusive of every day and holidays are work days. Therefore days should be a simple arithmetic value.