Duration calculating in partial days
Any idea why parent rows are calculating durations in partial days? None of our child rows has partial days. Here is a snippet of the plan:
Here are the project settings:
Thanks!
Answers
-
Might need to dig a bit further to identify the cause. Are these the only 5 tasks in the plan under Planning as a parent? Please share the list of all tasks (doesn't need to be the same name in your plan) under Planning as a parent with their duration and predecessors. Also help with the 5 holidays you've added (if they fall between the date ranges in this parent task).
Thanks,
Aravind