Duration calculating in partial days

Any idea why parent rows are calculating durations in partial days? None of our child rows has partial days. Here is a snippet of the plan:

Here are the project settings:

Thanks!

Answers

  • AravindGP
    AravindGP ✭✭✭✭✭✭

    Hi @meghan.hale66546


    Might need to dig a bit further to identify the cause. Are these the only 5 tasks in the plan under Planning as a parent? Please share the list of all tasks (doesn't need to be the same name in your plan) under Planning as a parent with their duration and predecessors. Also help with the 5 holidays you've added (if they fall between the date ranges in this parent task).

    Thanks,

    Aravind GP| Principal Consultant

    Atturra Data & Integration

    M: +61493337445

    E:Aravind.GP@atturra.com

    W: www.atturra.com