Resource Management allocation rounded
Hi,
i've a smartsheet project where i assigned myself on 1,5day (i.e. 12h for the business days from 15 december to 18 december, with 100% effort)
i linked the project to Res. Management, but when i see my allocation on SCHEDULE page, it results that i'm busy for 2 business days
There seems to be no match beetween days scheduled in smartsheet and allocation in resource management.
Any help?
Tags:
Answers
-
I believe RM uses dates plus allocation, not the duration. To accomplish a 1.5 hour day across two days of duration, I'd instead do 75% allocation from 15th to 18th.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives