why aren't 2 tasks showing in the critical path
There are 2 tasks which I am trying to show in the critical path:
"Customer waiting to get approval for VA" and "Virtual Appliance Download..."
I set the target dates, have the predecessors. What else do I need? I can see the critical path for the prior tasks. Please see the attached grid and gantt pics.
Best Answer
-
Hi Kathy, if pushing the end dates for those tasks didn't change the final project end date, they aren't critical path tasks. Critical tasks are those that cannot budge without impacting the project end date.
Answers
-
What happens if you push the end date on either of those tasks out by one day? Does it change the project end date?
-
Hi Julie,
Thank you for the suggestions. Unfortunately, that did not impact the critical path.
-
Hi Kathy, if pushing the end dates for those tasks didn't change the final project end date, they aren't critical path tasks. Critical tasks are those that cannot budge without impacting the project end date.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 466 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives