why aren't 2 tasks showing in the critical path
There are 2 tasks which I am trying to show in the critical path:
"Customer waiting to get approval for VA" and "Virtual Appliance Download..."
I set the target dates, have the predecessors. What else do I need? I can see the critical path for the prior tasks. Please see the attached grid and gantt pics.
Best Answer
-
Hi Kathy, if pushing the end dates for those tasks didn't change the final project end date, they aren't critical path tasks. Critical tasks are those that cannot budge without impacting the project end date.
Answers
-
What happens if you push the end date on either of those tasks out by one day? Does it change the project end date?
-
Hi Julie,
Thank you for the suggestions. Unfortunately, that did not impact the critical path.
-
Hi Kathy, if pushing the end dates for those tasks didn't change the final project end date, they aren't critical path tasks. Critical tasks are those that cannot budge without impacting the project end date.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67K Get Help
- 441 Global Discussions
- 154 Industry Talk
- 502 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 79 Community Job Board
- 512 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives