Visualization of % Complete by Parent
I want to be able to visualize % Complete by Parent, based on subtasks. I don't see any way to enter % complete on the subtasks, so is this impossible?
Answers
-
You'll need to set your project settings for the sheet to specify the % complete column.
In order to show the percentage completed for the parent task, you enter the percent completed for each of the children and the parent will automatically calculate
if you've setup the column correctly, you shouldn't be able to double click the parent row/s to enter the percentage completed without the following error being shown.
With my Progress Percentages, I use automation to automatically set this based on the Task Status;
Not Started = 0
In Progress = 50
Completed = 100
Cancelled = 100
On Hold = 0
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 62 Community Job Board
- 464 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives