Critical Path Duration

ap756
ap756
edited 03/02/24 in Smartsheet Basics

I was able to create tasks, define predecessors, and see the critical path associated with my project. Is there a way to see the duration of the critical path? In MS Project, I am able to see that my critical path is 113 days, for example. I can't find where I can the details of my critical path, past the tasks that fall into it.

Thank you!

Best Answer

  • Ric T
    Ric T ✭✭✭✭✭✭
    Answer ✓

    Hi @ap756,

    A suggestion; you could create a filter (screenshot below) to view tasks on the critical path.

    To calculate the duration, you could use a sheet summary or a metric sheet to pull through duration of tasks on the critical path. Example formula would be:

    =SUMIF([Critical Task?]:[Critical Task?], 1, Duration:Duration)

    Cheers,

    Ric

Answers