Critical Path Duration
I was able to create tasks, define predecessors, and see the critical path associated with my project. Is there a way to see the duration of the critical path? In MS Project, I am able to see that my critical path is 113 days, for example. I can't find where I can the details of my critical path, past the tasks that fall into it.
Thank you!
Best Answer
-
Hi @ap756,
A suggestion; you could create a filter (screenshot below) to view tasks on the critical path.
To calculate the duration, you could use a sheet summary or a metric sheet to pull through duration of tasks on the critical path. Example formula would be:
=SUMIF([Critical Task?]:[Critical Task?], 1, Duration:Duration)
Cheers,
Ric
Answers
-
Hi @ap756,
A suggestion; you could create a filter (screenshot below) to view tasks on the critical path.
To calculate the duration, you could use a sheet summary or a metric sheet to pull through duration of tasks on the critical path. Example formula would be:
=SUMIF([Critical Task?]:[Critical Task?], 1, Duration:Duration)
Cheers,
Ric
-
Thank you! I ended up calculating this way, but wasn't sure if there was a critical path view where it broke things down that I was missing. Thank you so much!
-
Happy to help :)
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives