Best way to adopt half day allowance

Options

I have a Smartsheet program spanning over 1 year which and I only want to include half days for work on Saturday. What is the best way to do this?

Answers

  • Genevieve P.
    Genevieve P. Employee Admin
    Options

    Hi @Johl

    There currently isn't a way to input a half day into the Project Settings of a Gantt sheet. You can select Saturday as a working day, however the "Length of day - Hours" will apply the same hours across all of your selected days.

    An alternative is to use Elapsed Time to allow a task to skip over any of your non-working days and see them as working hours, see: Duration and Predecessors

    Please submit your feature request to the Product team by creating an Idea Post in the Smartsheet Product Feedback and Ideas topic here in the Community.

    Cheers,

    Genevieve