Best way to adopt half day allowance
I have a Smartsheet program spanning over 1 year which and I only want to include half days for work on Saturday. What is the best way to do this?
Answers
-
Hi @Johl
There currently isn't a way to input a half day into the Project Settings of a Gantt sheet. You can select Saturday as a working day, however the "Length of day - Hours" will apply the same hours across all of your selected days.
An alternative is to use Elapsed Time to allow a task to skip over any of your non-working days and see them as working hours, see: Duration and Predecessors
Please submit your feature request to the Product team by creating an Idea Post in the Smartsheet Product Feedback and Ideas topic here in the Community.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives