Critical path & parent rows
I have a parent row (e.g. Testing) where the children (e.g. test 1, test 2, test 3,...) are performed in parallel & have the same finish date, so I often link the successor task(s) to the one parent row vs. each individual test task rows. Sadly, my critical path stops at the successor task when the predecessor is a parent row. Since the parent row shows what I need, I would like to avoid creating an additional task (e.g. All tests completed) row solely for this purpose of getting the critical path to work. Are there any other suggestions or workarounds?
Answers
-
Hi @CWibben
I personally cannot think of a different workaround at this time, but I understand your use-case and why this may be frustrating.
When you have a moment, please submit your feature request to the Product team by creating an Idea Post in the Smartsheet Product Feedback and Ideas topic here in the Community.
Thank you!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives