Dependencies- Start and End Date help
I am trying to automate the start and end date of Task #2 from Task #1. I have enabled dependencies in Smartsheet.
Here is the order of events- A deal closes on 9/29 (task #1/row #1), and then I need to do a knowledge transfer for 4 days from 9/30-10/3 (task #2/row #2)
For example: Under the "Predecessor" column on row #2, when I look to edit the Predecessor, I have input in the pop-up box:
Row #1- Deal Close- Type: Finish to Start; Lag-0
This automatically inputs the start and end date to be 9/30. However, I only want the start date set to 9/30... how do I automate in that I need 4 days to complete the task #2? Or, is the predecessor function/enabling dependencies only able to set dates for a 1-day start/end date?
(hope this makes sense)
Best Answer
-
There should be another column called "Duration". That's where you would put the 4 days.
Answers
-
There should be another column called "Duration". That's where you would put the 4 days.
-
Thanks @Paul Newcome , literally SMDH right now.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 448 Global Discussions
- 154 Industry Talk
- 504 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 512 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives