Total Float - No Longer Working - Returns Invalid Value
I added "Total Float" to my schedule in late March.
The calculation appeared to be working correctly at the time.
Over the past few weeks, I noticed more and more activities would return "#invalid value".
Now everything in the Total Float column as "#invalid value".
Is there something that I need to do to refresh this column?
I have tried to delete and replace the column. Note that "Dependencies" are turned on.
Best Answers
-
Hi @sdb60411
I agree that it would be helpful to see your sheet (without sensitive data). I know that TotalFloat does not always work if there are more than 1 predecessors listed in the row, so if you have multiple values in that column this could be the cause.
Cheers,
GenevieveJoin us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now -
Yes. I have multiple predecessors against many of the tasks. If it doesn't work with multiple predecessors, then that may very well be my issue.
Answers
-
Hi,
I hope you're well and safe!
Can you share some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi @sdb60411
I agree that it would be helpful to see your sheet (without sensitive data). I know that TotalFloat does not always work if there are more than 1 predecessors listed in the row, so if you have multiple values in that column this could be the cause.
Cheers,
GenevieveJoin us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now -
Yes. I have multiple predecessors against many of the tasks. If it doesn't work with multiple predecessors, then that may very well be my issue.
-
@Genevieve P. - I have a sheet with multiple predecessors on many of the rows. How can I caculate Total Float? Is this a product enhancement that has yet to be developed?
-
Hi @kdmarti24
Yes - here is the Product Idea you can vote on to submit your feedback to the Product Team:
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 351 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 135 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 443 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!