Enable Total Float to work with multiple predecessors.
Currently, Total Float will only calculate correctly when there is a single predecessor for an activity.
Sign in to see the current vote count, add your own vote, or leave a comment.
Yes, I would love to see this capability developed as well. Thank you!
This capability would be very useful for accurately showing which tasks are close to affecting critical path. As currently implemented, I don't see how TotalFloat can be used reliably since only the simplest of projects will not have some tasks with multiple predecessors.
This request was made almost a year ago and the discussion with moderator goes back even further. Does anyone know if its being worked on? Float/Slack is such a helpful/time saving piece of information when managing a schedule.
Another year down…almost. Any word? I had a cobble together my own highly specific code to very poorly approximate Total Float for my work. Our schedules are complex with heavy dependencies…and float is crucial for us.
Hope this gets resolved soon!
As one of the system admins, it is absurd to me that I cannot view or have access to all of the items created in my organization. We have over 11,000 reports, sheets, and dashboards and I can't see them. I have no visibility to if people are using our plan for their own personal use, or what kind of work is going on unless…
I noticed this the other day and tested Ctrl + M – it does not work. I submit ticket to Smartsheet support – they told me that’s expected behavior because it’s not currently available even though it still shows as keyboard shortcut in the menu🙄 and told me to submit new product idea. Please add this keyboard shortcut to…
Our sheets & workspaces require many people to have Admin level capabilities, which means that when someone requests access to a sheet or workspace, that email is sent to every Admin. This causes confusion and higher risk of no access granted (because people have learned to ignore the emails) or the wrong level of access…