where can a staff member assigned to a task write a detailed progress report for that task?
Jose Tirado
✭✭
If there a way in Smartsheet to document detailed progress reports for a task other than attaching a document to the row. I am looking for something similar to the attached picture, in which the team member is reporting progress on the task. what would be the best solution for this?
Answers
-
Hi @Jose Tirado
I would personally use the Conversations chat/comments for each row to note progress reports. Then in the grid of your sheet you could use the "Latest Comment" column to surface the last update:
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 438 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 451 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 283 Events
- 33 Webinars
- 7.3K Forum Archives