Report or Master Sheet with all the main tasks from multiple sheets to view on Gantt
pyou
✭
I have multiple sheets, one per product. Each sheets will have timelines for different tasks. How can I put together a Report or master Sheet with all the Tasks from across the Product sheets? I want to see all the timelines, for the main tasks, on 1 Gantt.
Answers
-
You can do this using a Report and selecting Gantt View.
IMPORTANT: The columns used to setup the Gantt (Start date column, End date column, and % Complete column) must have the same names in each source sheet.
-
Hi Jason, I've done this, but the report is unwieldy. Is there a way to just have the Task timelines and not the subtasks?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 438 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 451 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 283 Events
- 33 Webinars
- 7.3K Forum Archives