What's the difference between Timeline View and Gantt?
Best Answer
-
Gantt charts show the start/end dates of work and any dependencies. It'll clearly show when a delay in one area will impact another.
Timeline view shows the start/end dates of work without visualizing the dependencies and allows more flexible visualization and formatting (time period, grouping, etc.).
As a project manager, I'd use them differently:
Gantt chart: Use with project teams and certain highly engaged project stakeholders to show work progress and critical paths.
Timeline view: Use to produce reports for leadership or more general audiences.
Answers
-
Gantt charts show the start/end dates of work and any dependencies. It'll clearly show when a delay in one area will impact another.
Timeline view shows the start/end dates of work without visualizing the dependencies and allows more flexible visualization and formatting (time period, grouping, etc.).
As a project manager, I'd use them differently:
Gantt chart: Use with project teams and certain highly engaged project stakeholders to show work progress and critical paths.
Timeline view: Use to produce reports for leadership or more general audiences.
-
I see! Thank you so much for the great response.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 475 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives