After using Predecessor relationship FF, my dates below becomes incorrect

Options

After I give FF for Task2, it adjusts Task2 to complete by Task1 end date i.e 3/4/24. After that Task3 has dependency on 2, Task4 is dependent on task 3. But both these tasks have incorrect start date. And the duration for these tasks is only 1 day but still it considers 2 days instead of 1.

Answers

  • Genevieve P.
    Genevieve P. Employee Admin
    Options

    Hi @GAN

    There are hidden times associated with dates in Project sheets (you can see this by adding a Text/Number column and then using a formula to = the date + "" and turn it into text).

    In my task sheet the dates are appearing as expected, as are the hidden times. Is it possible the times in your rows are slightly different?

    How are the times set in your Project Settings:

    Cheers,
    Genevieve