How to calculate using a 7 day workweek (to replace NETWORKDAY)?
I am using this formula to calculate the # of days it takes to get to a particular task called, Enable. Range 2 = %Complete and Range 1 = Start Date of Enable. It calculates correctly using 5 days per week. I am now being asked to count using 7 days per week. Is there a comparable function that I can swap out for NETWORKDAY? I haven't found anything that works.
I have Gantt working days set to Sun - Sat.
Best Answer
-
Hey @Kathy PPT,
You should just be able to use NETDAYS(), as that counts every day between two dates.
Hope this helps!
If my response was helpful in any way (or answered your question) please be sure to upvote it, mark it as awesome, or mark it as the accepted answer!
I'm always looking to connect with other industry professionals, feel free to connect with me on LinkedIn as well!
Answers
-
Hey @Kathy PPT,
You should just be able to use NETDAYS(), as that counts every day between two dates.
Hope this helps!
If my response was helpful in any way (or answered your question) please be sure to upvote it, mark it as awesome, or mark it as the accepted answer!
I'm always looking to connect with other industry professionals, feel free to connect with me on LinkedIn as well!
-
@bisaacs,
Thank you, it worked. I knew it was something simple, just couldn't find it.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!