How do I report on the Intake Submission Date field from the Project Intake Sheet?
Kathy PPT
✭✭✭✭
Hi,
I'm using the PMO template. The "Intake Submission Date" column is system generated in the "Project Intake Sheet". Is there a way to pull this column into a report? When I create a report using the Project Intake Sheet, the Intake Submission Date does not show up as a field that I can select.
Project Intake Sheet and report using that sheet:
Tags:
Best Answer
-
Submission Date should show up as Created in the report.
Answers
-
Submission Date should show up as Created in the report.
-
Thanks that worked!