Issue with Duration/Date Range not rolling up

Hi everyone, I have a puzzle. I have a sheet that is all working except for this one spot, and it's affecting the rest of the sheet. I can't figure out what's wrong. The parent task will not display the end date or total duration for its section.
Dependencies are enabled on the sheet. This screenshot shows the whole section of tasks under a parent task (row 616). I've also included the task above it that is the predecessor for the section. (Ignore the gray cell. That's just from conditional formatting.)
I have tried changing durations, dates, and predecessors, but no luck.
(Also, note that the 1d duration is becoming 5 real days due to holidays designated in the project settings.)
Please, what am I missing? Thank you in advance!
Answers
-
This is bizarre. Can you copy/paste this into a new sheet and see if it's reproducible?
-
Well, it randomly started working a few hours later without making any changes, so I guess we'll never know. Thanks, @James Keuning , I appreciate you responding.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 206 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives