Issue with Duration/Date Range not rolling up

malden
malden ✭✭✭
edited 05/16/24 in Smartsheet Basics

Hi everyone, I have a puzzle. I have a sheet that is all working except for this one spot, and it's affecting the rest of the sheet. I can't figure out what's wrong. The parent task will not display the end date or total duration for its section.

Dependencies are enabled on the sheet. This screenshot shows the whole section of tasks under a parent task (row 616). I've also included the task above it that is the predecessor for the section. (Ignore the gray cell. That's just from conditional formatting.)

I have tried changing durations, dates, and predecessors, but no luck.

(Also, note that the 1d duration is becoming 5 real days due to holidays designated in the project settings.)

Please, what am I missing? Thank you in advance!

Answers