Working with % complete

I am sorry to ask what may be a very basic question, I am manually inserting the % complete in my smartsheet however my parent row displays the overall average as a "1" if 100% complete, how do i change this to show the parent row as "100%" complete.

What am i doing wrong

Screenshot 2024-05-23 at 18.08.24.png

Best Answer

  • eliweitz
    eliweitz ✭✭✭✭✭
    Answer βœ“

    Hey! Fret not, I might have a fix - there's a "%" format option in the upper toolbar (pictured below) that might do the trick. If the whole column contains percentages, then selecting the column header first, and clicking the "%" option should format the whole column in percent values.

    image.png

Answers

  • eliweitz
    eliweitz ✭✭✭✭✭
    Answer βœ“

    Hey! Fret not, I might have a fix - there's a "%" format option in the upper toolbar (pictured below) that might do the trick. If the whole column contains percentages, then selecting the column header first, and clicking the "%" option should format the whole column in percent values.

    image.png
  • Theresa Mc
    Theresa Mc ✭✭

    Rather embarrassed it was that simple! thank you! ( still learning)