We want to pull high-level dates from a project plan to add details on another sheet so it's easier to discuss. For example, we may have 'Topic Meetings' as a single line-item on the overall Project Plan, but on a meetings sheet we would have 'HR', 'Finance', 'Tech', etc. We turned off dependencies on the meetings sheet and I thought that would let me link dates. Should we create hidden columns to bring in the single-line dates as text? Even if so how do we calculate off of it? Use the Predecessors column on the Meetings sheet?
I would love your creative ideas!
Example:
Project Plan Sheet . . . Topic Meetings 3/1/24 - 3/15/24
Meetings Sheet . . .
UNDER 'Topic Meetings' we want it to bring in the overall 3/1/24 - 3/15/24, then underneath be able to say that 'HR' is line 1 SS, Finance is line 1 SS+1d, etc.
@kaelynbister @MattJ