Auto allocate % of project to tasks and auto calculate project completion
Hi all
Getting to grips with smartsheets and had a question.
Is it possible to auto calculate the % each task and sub task counts towards a project and also calculate how much % the project is complete based on completed tasks (hope that makes sense!)
For example. I have a project with 5 workstreams and each workstream as between 10-15 tasks.
So each workstream counts to 20% of the project (5x 20% = 100%)
Within each workstream, the sub tasks would have their own % count towards the 20% so if the workstream had 10 tasks, each task would be 2%.
There is also a running total of how much the project is completed, so as each task gets completed, this total would go up until all tasks are completed and the project is 100%
If more sub-tasks are added to the workstream, Smartsheets can auto calculate the new % each task is worth.
Thanks
Answers
-
Have you looked into project dependencies?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives