Unable to link to a date from one sheet to another

Answers
-
Editing to update:
I found the solution - the sheet I was linking start/duration from had the duration field as a Text/Number type, not Duration type. Once I changed the field type, the main sheet I was trying to get Finish populated for was able to recognize the duration and auto-calculate Finish.
I also have this problem and thought to use the start date and duration links, too, but it won't calculate my finish date even after pulling in start and duration - what can I do? I can try to use a formula but can't get one to work either because the finish field is a date format. I'm working in a larger plan and pulling in dates/% complete for a certain subset of tasks from a separate sheet so I cannot change the column properties/type either.
Ideas?
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 202 Use Cases
- 515 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 82 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives