How to exclude weekends while using formulas
I am very new to smartsheets and have just been playing with it and need guidance. I am trying to keep it as basic as possible. Essentially we are trying to backwards plan from our "due date" of when to begin our parts. i have it where you manually plug in a "shop time" and manually plug in a "outside lead time" have a formula to add the 2 together to get my "total lead time". You can then see the formula i have to get a start by date but am having trouble getting it to exclude weekends. I have read you cant have formulas and decencies so not sure what i need to do.
Answers
-
see how the networkday function works for you.
=NETWORKDAY([START BY DATE]@row,[DUE DATE]@row)
This function returns the number of working days between 2 dates. You could also add holidays into the function.
=NETWORKDAY([START BY DATE]@row,[DUE DATE]@row,[Holiday Date])
If you found this comment helpful. Please respond with any of the buttons below. Awesome🖤, Insightful💡, Upvote⬆️, or accepted answer. Not only will this help others searching for the same answer, but help me as well. Thank you.
-
what column should i put that formula?
-
Which ever column you want to show the the number of days in
If you found this comment helpful. Please respond with any of the buttons below. Awesome🖤, Insightful💡, Upvote⬆️, or accepted answer. Not only will this help others searching for the same answer, but help me as well. Thank you.
-
I am ideally wanting the start by date to reflect when we should start not including weekends based off the "total lead time" amount. Rather than showing a number.
-
is the total lead time a duration column? Or are you adding in the d manually?. If it is a text column it is reading is the value as a text value thus you would have to remove the d. If you have it as a duration column you do not have to add the d as it is automatic. how ever you would want to create a helper row to create a numeric value.
=WORKDAY([Due Date]@row, -Helper@row)
This would go in your start date column
See The screen shot.
The workday function also has an optional entry for holiday dates
=Workday(Date, Value, holiday)
If you found this comment helpful. Please respond with any of the buttons below. Awesome🖤, Insightful💡, Upvote⬆️, or accepted answer. Not only will this help others searching for the same answer, but help me as well. Thank you.
-
Strangly the first time I was building this formula it needed the helper column. Now it does not. so you can simply do
=WORKDAY([Due Date]@row, -[Total Lead Time]@row)
in the start date column.
Just be sure that Total Lead time is a duration column, Start date and due date are both date columns
If you found this comment helpful. Please respond with any of the buttons below. Awesome🖤, Insightful💡, Upvote⬆️, or accepted answer. Not only will this help others searching for the same answer, but help me as well. Thank you.
-
Mark, thank you very much that worked!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!