What do I need to change to make the "change cell value" work?
I have rebuilt this multiple times, I thought this one would work since I used a Path but the middle column is not populating in the sheet. The other two do populate. I have also tried to order them differently starting with "change cell value" but then the other two don't work. My only other option is to separate them out.
Automation 1: Change Cell Value
Automation 2: Assign people and Record Date
Best Answer
-
Each of those actions are considered to be final actions. This means you can't chain anything to after the action takes place. You are going to need to separate them out to three separate automations.
Answers
-
Each of those actions are considered to be final actions. This means you can't chain anything to after the action takes place. You are going to need to separate them out to three separate automations.
-
Thank you Paul!
-
Happy to help. 👍️
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.1K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 450 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 289 Events
- 34 Webinars
- 7.3K Forum Archives