Past Due Date in Business Day Formula
Hi! I have a formula I have been trying to figure out. I'm getting stuck because I want to make sure that the duration does not include weekends or holidays (if possible) and there is a condition.
Any help would be appreciated.
I would like to know how many business days past due a project is from today, but only if feedback received date has not been filled out.
Answers
-
Hi @Laura A
You can use the NETWORKDAY formula to get the working days between two dates. If the project is yet to be completed, you can still use the NETWORKDAY formula and use TODAY as the end date and Requested Due Date as the start date to get continuous aging.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!