Past Due Date in Business Day Formula

Laura A
Laura A
edited 06/19/24 in Formulas and Functions

Hi! I have a formula I have been trying to figure out. I'm getting stuck because I want to make sure that the duration does not include weekends or holidays (if possible) and there is a condition.

Any help would be appreciated.

I would like to know how many business days past due a project is from today, but only if feedback received date has not been filled out.

Answers

  • AravindGP
    AravindGP ✭✭✭✭✭✭

    Hi @Laura A

    You can use the NETWORKDAY formula to get the working days between two dates. If the project is yet to be completed, you can still use the NETWORKDAY formula and use TODAY as the end date and Requested Due Date as the start date to get continuous aging.

    Thanks,

    Aravind GP| Principal Consultant

    Atturra Data & Integration

    M: +61493337445

    E:Aravind.GP@atturra.com

    W: www.atturra.com

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!