Can anyone show me an example of negative float?
Berto_DA
✭✭
I know what it is, but I am trying to replicate it in a project plan.
Every time I try to do it, the End Date of the project just gets pushed out, making negative float impossible. I'm wondering if the project end date needs to be a fixed date that cannot be moved in order to do this.
If that is the case, is there a way lock in the end date of a project?
Tags:
Comments
-
Never mind. I created it.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!